Mon - No School MLK Day!
Tues - Go to CES Entrepreneur.com (https://www.entrepreneur.com/topic/ces)
Check out the slideshow on new products being shown at the CES convention.
Here Are the Things at CES You'll Actually Want to Buy
Provide a write up on one of the many products. Include a photo.
Wed - Friday
Students work on phase 1 of the garden.
Phase 1 consisted of clearing weeds, forming in brick walkway and installing underground PVC piping.
We begin in the garden.
We dig trenches and lay PVC pipe.
We also install a 4' x 16' brick walkway.
The finishing touches to phase 1. We backfill all of the trenches.
The craft women and men who helped with phase 1
The Finished Walkway, minus a few cuts.
Phase 1 complete. Phase two will begin next week. Phase two consists of finishing the smaller walkways, setting borders for planters and placing valves on the PVC risers placed in phase 1.